Welcome
to BostonConcreteCutting.Com
“We
Specialize in Cutting Doorways and Windows in Concrete Foundations”
Are You in Mattapoisett Massachusetts? Do You
Need Concrete Cutting?
We Are Your Local
Concrete Cutter
Call 781-519-2456
We Service Mattapoisett
MA and all surrounding Cities & Towns
Concrete
Cutting Mattapoisett MA Concrete
Cutting Mattapoisett Massachusetts
Concrete
Cutter Mattapoisett MA Concrete
Cutter Mattapoisett Massachusetts
Concrete
Coring Mattapoisett MA Concrete
Coring Mattapoisett Massachusetts
Core
Drilling Mattapoisett MA Core
Drilling Mattapoisett Massachusetts
Concrete
Sawing Mattapoisett MA Concrete
Sawing
Concrete
Cutting MA Concrete
Sawing Mattapoisett Mass
Concrete
Cutting Mattapoisett Mass Concrete
Cutting Mattapoisett Massachusetts
Concrete
Cutter Mattapoisett Mass Concrete
Coring Mass
Core Driller Mattapoisett MA Core Drilling Mattapoisett Mass
The
stirrups were hot-shrunk on the longitudinal bars. The helices for the concrete
columns were wound and attached to some of the vertical rods at the shop, to
preserve the pitch. The vertical rods in each concrete column project 6 inches
above the concrete floor line, and are connected to the bar placed on it, by a
piece of pipe 12 inches long. The concrete was a 1: 2: 4 mixtures. Giant
Portland cement was used and 1-inch trap rock. The placing of concrete was
begun about the middle of August, 1906, and the building was completed December
20. The McGraw Building, New York City, completed in 1907, is a good example of
a reinforced concrete building. The building has a frontage of 126 feet and a
depth of 90 feet, and is 11 stories in height. The height of the roof is about
150 feet above the street level. The building was designed to resist the
vibration of heavy printing machinery. The first and second concrete floors
were designed for a live load of 250 pounds per square foot; for the third concrete
floor, 150 pounds per square foot; for the fourth concrete floor and all concrete
floors above the fourth concrete floor, 125 pounds per square foot.
All
beams and girders were designed as continuous beams, even where supported on
the outside beams. There was two times more steel over the supports as in the
center of the spans. The Building Code of the City of New York requires that
the moment for continuous beams be taken as-!Ii at the center of the span, and
as over the support. These values are more than twice the theoretical value as
computed for continuous beams. One very interesting feature of this building is
that it was constructed during the winter. The first concrete was laid during
September, and the concrete work was completed in April. During freezing
weather, the windows of the concrete floors below the concrete floor that was
being constructed were closed with canvas; and salamanders (open stoves) were
distributed over the completed concrete floor, and kept in constant operation.
Coke was used as the fuel for the salamanders. The concrete was mixed with hot
water, and the sand and the stone were also heated. After two or three stories
had been erected, and the construction force was fully organized, a concrete
floor was completed in about 12 days. Three complete sets of concrete forms
were provided and used. They were usually left in place nearly three weeks. In
Fig. 206 are shown the -plans of stairs constructed in the Fridenberg
building at 908 Chestnut Street, Philadelphia. This building is 24 feet by 60
feet, and is seven stories high. Structurally the building was constructed of
reinforced concrete. The stair and elevator tower is located in the rear of the
main building. The plans of the stairs are interesting on account of the
long-span (about 16 feet) concrete slab construction. The stairs were designed
to carry safely a live load of 100 pounds per square foot; and in the
theoretical calculations the concrete slab was treated as a flat concrete slab
with a clear span of 16 feet.
The
shear bars were wide and spaced as shown in the details. The calculations
showed a low shearing value in the concrete, but stirrups were used to secure a
good bond between the steel and concrete. The concrete was a 1: 2: 4 mixtures,
and was mixed wet. The reinforcing steel consisted of square deformed bars,
except the stirrups, which were made of 1-inch plain round steel. An
interesting feature of a large reinforced-concrete building constructed for the
General Electric Company at Fort Wayne, Ind., is the design of the lintels. As
shown in Fig. 207, the bottom of the lintel is at the same elevation as the
bottom of the concrete slab. The total space between the concrete columns is
filled with double windows; and the space between the bottom of the windows and
the concrete floor is filled with lintels and a thin concrete wall of
reinforced concrete, as shown in the figure. The picture illustrate sections of
the concrete walls of the pure water basin and the 50- foot circular concrete
tanks which have been partly described in Part 1 under the heading of
Waterproofing.
Are You in Mattapoisett Massachusetts? Do You
Need Concrete Cutting?
We Are Your Local
Concrete Cutter
Call 781-519-2456
We Service Mattapoisett
MA and all surrounding Cities & Towns