Welcome
to BostonConcreteCutting.Com
“We
Specialize in Cutting Doorways and Windows in Concrete Foundations”
Are You in Wareham Massachusetts? Do You
Need Concrete Cutting?
We Are Your Local
Concrete Cutter
Call 781-519-2456
We Service Wareham MA
and all surrounding Cities & Towns
Concrete
Cutting Wareham MA Concrete Cutting
Wareham Massachusetts
Concrete
Cutter Wareham MA Concrete Cutter
Wareham Massachusetts
Concrete
Coring Wareham MA Concrete Coring
Wareham Massachusetts
Core
Drilling Wareham MA Core
Drilling Wareham Massachusetts
Concrete
Sawing Wareham MA Concrete Sawing
Concrete
Cutting MA Concrete
Sawing Wareham Mass
Concrete
Cutting Wareham Mass Concrete Cutting
Wareham Massachusetts
Concrete
Cutter Wareham Mass Concrete Coring Mass
Core Driller Wareham MA Core
Drilling Wareham Mass
A
concrete waterway of 18 feet was required in the canal span by the State Canal
Commissioner, and this passage was arranged under the center of the arch. The concrete
piles were driven by means of a scow. The cap for the concrete piles was a 3 by
12-inch timber. Plank 2 inches thick were sawed to the correct curvature, and
nailed to the 2 by 12-inch joists, which were spaced about 12 inches apart. The
lagging was one inch thick, and was nailed to the curved plank. The wedges were
made and used as shown. The centering was constantly checked; this was found
important after a strong wind. The centering for the other two of the main
arches was constructed similarly to that-of the arch shown. After some
difficulty had been experienced in keeping the forms in place during the
concreting of the first arch, the concrete for the other arches was placed as
shown in Fig. 172, and no difficulty was encountered. Sections 1 and 1 were
first placed, then 2 and 2, finishing with section 6. The concreting on the
canal span was begun November 1, and finished November 12; and the forms were
lowered by means of the wedges five weeks later. The deflection at the crown
was 0.5 inch, and after the spandrel concrete walls were built and the fill
made, there was an additional deflection of 0.4 inch. In building the forms, an
allowance of part of the span was made, to allow for this deflection. The
deflections at the crown of the other three arches were 0.6 inch, 1.45 inches,
and 1.34 inches. The full bending details of the bars should be made before the
reinforcing steel is ordered for any reinforced-concrete work that is to be
constructed. It has been the common practice for contractors to make these details,
if they are made; and they may or may not submit them to the designing
architects or engineers for their approval. Very often the plans or
specifications do not state how long the bars are to be, or even state what lap
of the bars is required; or they may not be very definite in the number of bars
to he turned up in the concrete beams and girders. If architects and engineers
would make these details and submit them with their general drawings, the concrete
contractors could then make a very definite estimate on the amount of steel
required for the work, and these details should also assist the contractor in
estimating the cost of the bending of the bars. With the assistance of these
details being made very definite, it should not only assist the contractor in
making his bid on the work, but would often result in better work being done. The
angle, at which the diagonal bars are turned up, varies from about 10 degrees
to 45 degrees, and sometimes to a greater angle than 45 degrees. A great deal
depends upon the length and depth of the concrete beam or girder. If the concrete
beam is very short and deep, the bars are usually turned up at an angle of
about 45 degrees, or perhaps a little greater; but if the concrete beam is long
and shallow, the angle at which these bars are turned is very small. This
angle, in the average practice, is about 30 degrees. The bending of the bars is
usually a simple matter, and generally can he easily and quickly done. If bends
of 30 degrees or more, with short radii, are required of large bars-1 inch to 1
inches square—it is usually necessary to heat the bars. This makes the bending
more expensive, as it requires the use of forges and blacksmiths to do the
work. The usual outfit for bending the bars cold consists of a strong table, a
vise, and a lever with two short prongs. The outline to which the bar is to be
bent is laid out on the table, and holes are bored at the point where the bends
are to be made. Steel plugs 5 inches to 6 inches long are then placed in these
holes. Short pieces of boards are nailed to the table where necessary, to hold
the bar in place while being bent. The bar is then placed in the position A-B,
Fig. 173, and bent around the plugs C and D, and then around the plugs B and F,
until the ends EH and FG are parallel to AB. The building was constructed
structurally of reinforced concrete, except the first concrete floor and the concrete
columns in the lower concrete floors. The concrete floors were all designed to
carry 200 pounds per square foot. The side concrete walls were constructed of
light-colored brick, and trimmed with terra-cotta. The first concrete floor was
constructed especially to suit the requirements of the chemical company that is
to occupy the building for several years. If this company should leave the
building when their present lease expires, it will very probably be necessary
to reconstruct the first concrete floor; and therefore it was constructed of
structural steel, as it will be much easier to remove a concrete floor
constructed of structural steel than one constructed of reinforced concrete. The
footings for each of the interior concrete columns were designed as single
footings. They were 10 feet square, 30 inches thick, and were reinforced as
shown in Fig. 188. The concrete columns in the basement, first, and second concrete
floors, were of structural steel, and fireproofed with concrete. The concrete
wall concrete columns were either square or rectangular in shape and the interior
concrete columns were round, being twenty inches in diameter. The stress
allowed in the structural steel of these concrete columns was 16,000 pounds per
square inch of the steel section; but no allowance was made for the four small bars
placed in the concrete column. These steel cores were provided with angle
brackets to support the concrete beams, and with spread bases to transmit the
stress in the steel to the concrete foundation. The cores are composed of
angles and plates, and are riveted together in the usual manner. The concrete
columns were built in sections of a length equal to the height of two stories.
The extra metal required in this practice was very small; and the expense of
half the joints, if a change of section had been made at each concrete floor,
was saved. The general outline and
details of these steel cores are illustrated in Fig. 189 In the exterior concrete
columns, the steel cores were used in the basement and the first, second, and
third concrete floors, where necessary; in the interior concrete columns, they
were used also in the fourth story, and in two concrete columns the structural
steel extended to the sixth concrete floor line. The exterior concrete columns
above the structural steel, and also the concrete columns in which structural
steel was not required, were in general reinforced with 8 bars 1 inch square,
in the lower concrete floors; and this amount of steel was gradually reduced to
4 bars 1 inch square, in the seventh story. In the interior concrete columns,
the reinforcement above the steel cores consisted of 8 bars 1 inch square, in
the concrete floor just above the structural steel; and the number of these
bars was gradually reduced to 4 in the seventh concrete floor. The concrete
floor-concrete slab was 5 inches thick, and was reinforced with - inch square
bars spaced 6 inches and (156)1-inch bars were placed in the concrete slab near
the top, at right angles to the girders. The bars were 12 inches center to
center, and were placed over the center of the girders. The concrete wall beams
or lintels on the Fifth Street and Appletree Street
sides of the building are shown in section in Fig. 191. They are 9 inches by 24
inches, and are reinforced with 2 bars 1 inch square. The concrete wall girders
in the side of the building opposite Appletree Street
are 14 inches by 24 inches, and are reinforced with 6 bars 1 inch square. The
stairs were constructed as shown in Fig. 192. The structural concrete slab was
6 inches thick, and was reinforced with - inch bars. Safety treads 52 inches in
width, and 12 inches shorter than the width of the stairs, were set in each
step. The concrete for the concrete beams, girders, concrete slabs, and
footings was a 1: 2: 5 mixtures; and for the concrete columns, a 1: 2: 4
mixtures were required. The stone used in this concrete was trap rock. The
concrete was mixed in a batch concrete mixer, and the consistency of the
mixture was what is commonly known as a wet mixture. Square twisted bars were
used as the reinforcing steel. The first, second, and third concrete floors
were finished with 1k-inch maple concrete flooring: The stringers, 2 inches by
3 inches, were spaced 16 inches apart, and the space between the stringers was
filled with cinder concrete. The other concrete floors were finished with a
one-inch coat of cement finish. A cinder fill 2 inches thick was laid on the
concrete floor-concrete slab, on which was laid the cement finish. The cinder
concrete consisted of 1 part Portland cement, 3 parts sand, and 7 parts
cinders. The cement finish was composed of 1 part Portland cement, I part sand,
and 1 part '-inch crushed granite. Fig. 193 shows the plan of the concrete
foundations and the typical layout of the structural members for each concrete
floor of a building constructed by Cramp & Company.
Are You in Wareham Massachusetts? Do You
Need Concrete Cutting?
We Are Your Local
Concrete Cutter
Call 781-519-2456
We Service Wareham MA
and all surrounding Cities & Towns