Welcome
to BostonConcreteCutting.Com
“We
Specialize in Cutting Doorways and Windows in Concrete Foundations”
Are You in Westport Massachusetts? Do You
Need Concrete Cutting?
We Are Your Local
Concrete Cutter
Call 781-519-2456
We Service Westport
MA and all surrounding Cities & Towns
Concrete
Cutting Westport MA Concrete Cutting
Westport Massachusetts
Concrete
Cutter Westport MA Concrete Cutter
Westport Massachusetts
Concrete
Coring Westport MA Concrete Coring
Westport Massachusetts
Core
Drilling Westport MA Core
Drilling Westport Massachusetts
Concrete
Sawing Westport MA Concrete Sawing
Concrete
Cutting MA Concrete
Sawing Westport Mass
Concrete
Cutting Westport Mass Concrete Cutting
Westport Massachusetts
Concrete
Cutter Westport Mass Concrete Coring
Mass
Core Driller Westport MA Core
Drilling Westport Mass
The bar which forms the band is bent close
around each vertical bar in the concrete columns, and therefore assists in
holding these bars in place. The bands for the rectangular concrete column b
are made up of two separate bands for holding the bars in place in concrete
beams and girders, have been successfully used. These spacers are made of heavy
sheet iron. They are fastened to the stirrups by means of the loops in the
spacers. The ends of the spacers which project out to the forms of the sides of
the concrete beams should be made blunt or rounded. This will prevent the ends
of the spacers being driven into the forms when the concrete is being tamped.
The number of these spacers required will depend on the lengths of the concrete
beams; usually 2 to 4 spacers are used in each concrete beam.
Among the patented methods of fastening the
bars together for concrete beams and girders, is the Unit Girder Frame System.
The loose bars are bent and made into a frame as shown in Fig. 183. All this
work is done in a shop; and the frames are sent to where the building is being
constructed, ready to be placed. The stirrups are made of round or flat bars,
and are hot-shrunk on the longitudinal rods. The girder, concrete beam, or concrete
column unit is shipped to the site of the building being constructed, bearing a
tag numbered to correspond with a number on the plan showing the proper
position of the reinforcement. The place and manner of making breaks or joints
in concrete floor construction at the end of a day's work, is a subject that
has been much discussed by engineers and construction companies. But there has
not been any general agreement yet as to the best method and place of
constructing these joints. Wherever joints are made, great care should be
exercised to secure a bond between the new and the old concrete.
Fig.
184 shows a sectional view of one method of making a break at the end of the
day's work, which has been used very extensively and successfully. The stirrups
and concrete slab bars form the main bond between the old and the new work, if
the break is left more than a few hours. Short bars in the top of the concrete
slab will also assist in making a good bond; also, an additional number of
stirrups should be used in the concrete beam where the break is to be made.
Before the new concrete is placed, the old concrete should be well scraped,
thoroughly soaked with clean water, and given a thin coat of neat cement grout.
An objection to this method of forming a joint is that the shrinkage in the
concrete may cause a separation of the concrete placed at the two different
times, so that water will find a passage. The top coat that is generally placed
later will greatly assist in overcoming this objection. Another method of
forming stopping-places is by dividing the concrete beam vertically that is,
making two L-concrete beams instead of one concrete T- beam.
This
is a very good method, but practically it is found difficult to construct the
forms dividing the concrete beam, as the steel is greatly in the way. The
method of stopping the work at the center of the span of the concrete beams and
parallel to the girders has been used to some extent. Fig. 186 illustrates this
method. Theoretically the concrete slab is not weakened; and as the maximum
bending moment occurs at this point, the shear is zero, and therefore the
326 concrete
beams are not supposed to be weakened, except for the loss of concrete in
tension, and this is not usually considered in the calculation. The bottoms of
the concrete beams are tied together by the steel that is placed in the concrete
beams to take the tensile stresses; and there should be some short bars placed
in the top of these concrete beams, as well as in the top of the concrete slab,
to tie them together.
The
objection made in the description of the first method—in that any shrinkage in
the concrete at the joint will permit water to pass through—is greater in the
second and third methods than in the first. Fig. 187 shows the typical
structural concrete floor plan, above the first concrete floor, of a building
constructed for Buck at Fifth and Appletree Streets,
Philadelphia. The architects were Ballinger & Perrot, and the building was constructed
by Cramp & Company, Philadelphia. The building has a frontage of 90 feet on
Fifth Street, and a depth of 61 feet on Appletree
Street, and is seven stories high.
Are You in Westport Massachusetts? Do You
Need Concrete Cutting?
We Are Your Local
Concrete Cutter
Call 781-519-2456
We Service Westport
MA and all surrounding Cities & Towns